1810 McHenry Library Addition & Renovation
Phase 1: addition of approximately 120,000 ogsf to the existing 156,000 ogsf building.
Phase 2: renovations, ADA improvements, and seismic reinforcement of the existing building.
For more information on this project, see the McHenry Library Addition and Renovation Project page.
|
|
74,000,000.00 |
|
|
Alteration |
|
|
Bret A. Caton |
|
|
Construction |
|
|
Phase 1: Construction Completed Phase 2: Construction Documents Completed, estimated start date January 2008. |
|
|
|
|
|
BOORA Architects, Portland |
|
|
January 2002 |
|
|
October 2005 |
|
|
|
|
|
April 2009 |
|
|
|
|
|
|
|
|
Materials Testing RFQ Advertisement |