9078- Dark Fiber Optic Upgrade

by Sadie Miles last modified 2008-07-21 11:46 AM

Install underground conduit from the West entrance of campus to the West remote lot and from the 2300 Delaware property line (fronting Delaware Ave.) into the Building A data room. Then install one inch inter-duct in all of the new conduit and in some existing conduit between the West remote lot and the Physical Science Building. This work is part of a much larger project to bring additional connectivity to the campus.

0.00

Alteration

Kevin Foisie

Construction Documents









9078- Dark Fiber Optic Upgrade Planning
Information about planning for this project.

« August 2008 »
Su Mo Tu We Th Fr Sa
          1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30